GEPL Projects

Major Projects

YEARPROJECTCLIENTSCOPEVALUE
 
2018/19West Angelas Enabling WorksRio TintoEnabling Works for Deposit C&D – Clearing, Bulk Earthworks, Culverts Installation, Bore Water Supply, Cement Stabilisation, Surfacing$16M
2017/18Phils Creek Landbridge – Stage 1Rio TintoInitial Scope & Stage of work to realign Phils Creek. Bulk Earthworks, 10,000,000T placed and compacted, Dust Suppression$4.5M
2018/19Phils Creek Landbridge – Stage 2Rio TintoScreening, Bulk Earthworks, Detailed Earthworks, Rock Armour Protection, Powerline & Dewater infrastructure Relocation to result in the reinstatement of Phils Creek to original alignment.$8M
2018/19Yandi RocksortBHPRock Sort and Stockpiling of 125,000 tonnes of facing class & 1/4T sized rock$2.4M
2018/19Warehouse Yard Upgrade – Yandi & Brockman B2/B4Rio TintoScope of Works undertaken through fully operational warehouse compounds, Earthworks, Drainage, Cement Stabilisation, Surfacing.$2.25M
2018/19Bina Bina YandiRio TintoClearing, Bulk Earthworks, Haul Road Construction, Dust Suppression$2M
2019Hope Downs 1 – Plant & Labour SupplyRio TintoSupply of Plant & Labour to facilitate ROM Pad activities – loading of crusher and rock breaking$1.7M
2019Parabudoo – Down Hill Haulage Road UpgradeRio TintoUpgrade of various haul road sections within the mine pit area to meet regulations$800K
2018/19Upgrades and Remedial Works – YandiRio TintoCulvert Installation, Road surface repairs, W-Barriers and Audio Strips$1.5M
2018/21General Road MaintenanceShire of AshburtonRoad and floodway repair & maintenance$1M
2017/18Shut Down WorksRio TintoSupply of Plant and Personnel to Shutdown Activities – Day Shift / Night Shift$250K
2017/18General Road MaintenanceDBCAUnsealed Road and Floodway Repair & Maintenance$220K

Working with some of Australia’s largest government and private sector organisations.